Start date : Jun 27, 2023 ( NOT FLEXIBLE )
Estimated completion date : Jun 28, 2023
Total bid amount : $13300
- Heating & Cooling, HVAC, Air-conditioning
- Upgrade
- 2500
- Heat Pump and Ducts
- Make it optional on the bid
- N/A
-
hello, we need a new heat pump installed, the house is two story, about 1200 each, and we need two zones.
Thanks
- Item
- Count/Description
sam phong
Jun 27, 2023
Jun 28, 2023
Jul 09, 2023
completion
13300
replace old furnace to new 5 ton air handler, install one new Gree flex Flexx60hp230v1a0 5 ton 17 seer variable speed heat pump, lineset, electrical, draining, 00224 Emerson thermostat, install two zone control first floor and second floor, check and seal duct leaks., total labors and materials for $13,900.
Everything for the above scope of work, Emerson thermostat
NA
five years warranty labors and materials
$13300